This step will RECEIVE the PTFs, analyze the environment for any Pre APPLY HOLD conditions that need to be handled, then run an APPLY CHECK to analyze the target environment and prepare subsequent steps of the upgrade.
NOTE:
A log is displayed. For general information about understanding the log, see Maintenance job logs.
When the status PreHold is displayed in Green it indicates that handling of all Pre Holds has been confirmed (as above). Use 'S' to re-run the RECEIVE and ANALYZE job.
Do the following, as necessary:
NOTE: If the job completes with status PE-PTF, and you intend to install the resolving PTFs together with this upgrade (recommended), use the A line command. The response to the A command depends on the method that you chose in Step 1.2 – Verify Upgrade Files for obtaining the required files:
You do not need to specify requisite PTFs, as they will be automatically RECEIVEd together with the specified PTF(s).
When the dataset is present, it is moved to the bottom of the panel with a Ready status (or with an *Empty* status if the dataset is empty - in which case the PTFs must copied into the dataset), and the name of the next dataset to be used is displayed at the top.
If you chose to continue without the resolving PTFs, manually mark this step COMPLETE.
Parent Topic |