Editing Forecast/BIM rule

This procedure describes how to edit a Forecast/BIM rule, which enables you to revise expected run times.

To edit Forecast/BIM rule:

  1. From the Forecast domain, click Forecast/BIM Rules.

    The Forecast/BIM Rules window appears.

  2. In the left pane, select one of the rules.

    The fields appear in the right pane.

  3. Update the fields, as described in the following field descriptions, and click Advanced to set the calendar details:
  4. Click OK.

    The rule appears in the left pane.

  5. Do one of the following:
  6. Add rules, as described in Creating a Forecast/BIM rule.
  7. Click Save.

    The Forecast/BIM rules you edited are saved, and the checked ones are enabled.

Parent Topic

Forecast/BIM rules