Job scheduling is affected by other factors. For example, a cyclic job can be defined using one of the following methods, as described in Scheduling a job/folder and Setting Cyclic jobs:
Control-M/Server sorts the times entered in Specific Times and runs the job starting from New Day time (or Order time) according to chronological order, until the next New Day time.
If Cyclic Job is not selected, the job is not affected by the settings.
To provide logic to stop a cyclic job (for example, if the job ends Not OK), create the relevant On statement followed by a Do Stop-cyclic statement in the Actions tab, as described in Creating Notifications and On-Do Actions.