Upgrading Control-M/Agents

This procedure describes how to transfer installation packages to existing Control-M/Agents and upgrade them to the current base version or fix pack on UNIX, Windows, or AS400.

NOTE: (Windows only) An upgrade does not begin until all jobs have ended, unless you selected Force Upgrade in a Retry.

NOTE: You cannot upgrade more than one Control-M/Agent on the same Windows computer simultaneously.

To upgrade Control-M/Agents:

  1. From the Manage tab, select Deployment.

    The Deployment window appears.

  2. Click New Activity > Agent> Upgrade.

    The Upgrade Control-M Agents Activity window appears.

  3. Do the following:
    1. In the Activity Name field, accept the default or type a new name for this activity.
    2. In the Description field, describe the purpose of this activity (optional).
    3. In the E-Mail Notification field, type the email address(es) that you want to receive notifications about this activity (optional).

      To receive email notification, you need to define the email server parameters, as described in SMTP parameters.

  4. Select one of the following:

    NOTE:

  5. Click Next.
  6. From the Upgrade Agents to Version drop-down list, select the version or fix pack that you want to upgrade to and then select the Control-M/Agent(s) that you want to upgrade.

    The list of values depends on the Agent installation packages in your repository. For more information, see Copying Control-M/Agent installation packages.

  7. Depending on which method you selected, click Transfer or Upgrade.

    The transfer process starts and progress messages appear in the right pane of the deployment activity. To view and troubleshoot the internal stages of the upgrade, click Log from the Agent Deployment window. If you selected to transfer the installation package, you can upgrade the Control-M/Agent(s) any time after the transfer is complete. A job runs on the Control-M/Agent(s) to verify that it upgraded successfully.

Parent Topic

Control-M/Agent deployment