6102 Timeout waiting for LG process to change state to Running

Explanation: This utility is suspended while the Control-M/Server state is Suspended and resumes running when it notices that the Control-M/Server state is Running. The utility waits for it to resume Running state, but the timeout limit is exceeded.

The utility aborts. If ordering performs, it continues with the ordering attempts of the rest of the jobs.

Corrective Action: Check the Control-M/Server processes state with the prf utility and try again when the processes return to Running state.

Parent Topic

Control-M/Server Messages