Days And/Or

Indicates the relationship between specified Days parameter values and Week days parameter values.

Additional information

Description

Usage

Optional

Format

Valid values:

  • and
  • or (default)

Invalid Characters

Non-English characters

Variable Name

None

Alternate names

  • Control‑M/EM Utilities: DAYS_AND_OR
  • Control-M Report: DAYS_AND_OR
  • Control-M/Server Utilities: -cal_andor
  • Control‑M for z/OS: And/Or
  • Control-M/EM API: and_or

If And is specified, both the Days/Days Calendar criteria and Week Days/Weeks Calendar criteria must be satisfied for a job to be scheduled.

NOTE: If the And option is selected (Month Days and Weekdays), and no criteria are specified for either the Month Days or the Week Days parameter, Control-M/EM assumes that ALL has been specified for the empty parameter. For example, if Monday is selected, and no days of the month are selected, the job is scheduled on all Mondays of the month.

If Or is specified, either the Days/Days Calendar criteria or Week Days/Weeks Calendar criteria must be satisfied for a job to be scheduled.