Points to Remember Concerning SMART Table Scheduling
Before ordering the SMART Table Entity and its jobs, note the following points about SMART Table scheduling:
Only the SMART Table Entity can be ordered. Individual jobs in the SMART Table cannot be ordered, although they can be forced.
When a SMART Table Entity is ordered, its schedule RBCs are checked to see if the SMART Table Entity is eligible for scheduling. If none of the sets of scheduling criteria for the SMART Table Entity is satisfied, neither the SMART Table Entity, nor any of its jobs, are ordered. In this case, even if the basic scheduling criteria of the job itself are satisfied, and an OR relationship is defined, the job is not scheduled.
If at least one set of scheduling criteria is satisfied, each job is checked to see if it can be scheduled according to the combination of its schedule RBCs, basic scheduling criteria, and the defined AND/OR relationship.