Defining automatic rerun for a job that ends Not OK example

This example describes how to define an automatic rerun for a job that ends not OK, which triggers an alternative job and sends an alert.

To automatically rerun a job that ends Not OK:

  1. In the Scheduling tab, Rerun Settings area, select the Cyclic checkbox and then click Set.
  2. The Cyclic Job Run Times window appears.
  3. In the Rerun Interval section, select Rerun Every 1 minute and then in the All Intervals are from Job's field, from the dropdown list select End.
  4. Click OK.
  5. In the Maximum Reruns field, select 1 for the number of reruns.
  6. From the Actions tab, click Add_Parameter to add an On-Do Action.

    The On Do Actions window appears.

  7. In the On field, from the dropdown list select Job ended Not OK.
  8. In the Do field, select Do Rerun.
  9. Click Add Do and then in the Do field from the dropdown list, select Order Job (ignore Scheduling Criteria) and then type the following:
  10. Click Add Do and then in in Do field, from the dropdown list, select Notify and then add the following: