The following table describes the Host rule. The parameters can be defined to simulate a job that runs during a planned downtime of a Control-M Server or specified host/host group. This enables you to better plan for possible downtime of servers when defining your job flows.
Parameter |
Description |
---|---|
Control-M Server |
Defines the name of the Control-M Server that participates in the simulation of the What-If Host scenario. NOTE: If the none option is selected, the simulation takes into account all Control-M Servers defined. |
Host/Host Group |
Defines the name of the host/host group to shut down. NOTE: If none or the Select All option is selected, the simulation takes into account all host/host groups defined. |
From: New Day Time/Time |
Defines the start of the downtime. |
Until: End of Simulation Time/Time |
Defines the end of the downtime. |
Calendar details (click Advanced) Applies to Service Assumption |
|
Calendar |
Details of the Control-M and calendar to be used to schedule the job. |
Period |
Name of one or more periods for this exception definition, which can be selected from a list. Special month rules are not supported. |
Parent Topic |