Defining a Folder Rule-based Calendar

This procedure describes how to define a Folder RBC, which enables you to schedule a Folder RBC in a SMART Folder.

Before you begin

Ensure that you open the Workspace folder that holds the job you want to schedule and that you select SMART folder, as described in Workspace management.

To define a Folder Rule-based Calendar:

  1. In the Workspace, select the folder.
  2. Click Details or click the folder.
  3. Select the Scheduling tab.
  4. From the Rule-based Calendar List, click Add_Parameter.
  5. Select Folder Rule-based Calendar.

    To create a pre-defined Control-M Rule-based Calendar, see Creating a Control-M Rule-based Calendar.

  6. In the Rule-based Calendar dialog box, type the Rule-based Calendar name.
  7. From the Schedule drop-down list, select a scheduling type, as described in Scheduling options.
  8. To graphically view your scheduling, click View Schedule.
  9. Click More, and set the Scheduling parameters.

    A Folder RBC is created and you can select it for scheduling. Jobs and sub-folders can be selected in the folder for scheduling.

Parent Topic

Folders