The following procedure describes how to schedule Jobs on month days.
To schedule Jobs on month days:
Select the Job/Folder you want to schedule in the Workspace.
The Job properties pane appears on the right.
Click .
The Job properties are enabled for definition.
Select the Scheduling tab.
From the Schedule drop-down list, select Advanced.
Click .
In the Month days area, you can do one of the following:
From the Order tab, order a Job on a selected day, by selecting a day.
From the End of month tab do one of the following:
Select a working day or days from the end of the month on which the Job will be ordered on every month. When you select the day, choose the On day from end of month option. For example, if you select L1 the Job is ordered one day before the end of the month. If the month is 30 days, the Job is ordered on the 29th.
Select a working day or days from the end of the month on which the Job will not be ordered on every month. When you select the day, choose the On all days except on selected day from end of month option. For example, if you select -L1 the Job is not ordered one day before the end of the month. If the month is 30 days, the Job is ordered on all days of the month except the 29th.