This procedure describes how to check-in a Workspace, which enables you to save your definitions to the Control-M database.
NOTE: This option must be enabled by your Control-M Administrator.
To check in a Workspace:
From the Workspace, in the ribbon, click .
A confirmation message appears.
Click Yes.
Check-in is in progress. There are three stages of check-in; verifying check-in requirements, check-in Folders, synchronizing Folders with the Control-M/Server database. If check-in succeeded for all three stages, a confirmation message appears indicating that check-in succeeded.
Do the following if check-in fails:
Check-in failed due to validation errors found upon check-in. You must fix those errors and try to check-in again. Take note that some warnings are mandatory and also must be fixed for check-in. These types of warnings are indicated by in the Validation panel.
There is a check-in error due to updating Jobs/Folders that you are not authorized to change, and they require a Control-M scheduler's approval. You can view these items in the Authorizations panel. You can rollback changes and continue check-in or submit the Workspace as a request.
There is a check-in error due to conflicts found upon check-in. Some of the Jobs/Folders that you have modified were modified by another user. you can do one of the following:
Overwrite all: Overwrite all changes that were made by other users. Take note, this option is disabled when there are a number of different conflicts that cannot be overwritten at once.
Cancel and see conflicts: View the conflicts in the conflicts tab in the bottom pane, and resolve each conflict individually.
Check-in succeeded with synchronization exceptions due to connection issues, in this case you can check later if the Folders are synchronized or contact your Control-M administrator.