The job is selected for restart

If a job fails and its job scheduling definition indicates that the job is restarted following such a failure, the job can be automatically restarted.

Jobs are placed in WAIT SCHEDULE status in the Active Environment screen until all conditions required for the execution are fulfilled (time limits, prerequisite conditions, Quantitative resources, Control resources, and so on.). When all conditions for the execution of a job have been fulfilled, the JCL of the job to be restarted is prepared for submission.

Any job under Control-M can be restarted, even if the job scheduling definition does not contain restart parameters. In this case, restart is manually requested from the Active Environment screen.

Parent Topic

Basic Control-M/Restart process overview