ODATE

You have seen the term ODAT several times when using date references in conditions in IN and OUT and DO COND statements. ODAT is a four-letter abbreviation of ODATE; the term is abbreviated in conditions because the date field of conditions only allows entry of four characters.

ODATE is a keyword that means Original scheduling date, and it refers to (and resolves to) the working date on which the job was originally scheduled.

The important points to note are that:

The ODATE allows Control-M (and you) distinguish between different orders of the same job, and determine which job order of the job applies to which date. The same applies to conditions.

Parent Topic

System Date, Working Date and ODATE