Displaying the Scheduling Plan for the Job

Before beginning to define IDJOB4, display the schedule plan for IDJOB3.

Option P (PLN) in the Job List screen is used to request a graphic display of a schedule for job planning.

Figure 23 Option P (PLN)

JOB LIST     LIB: CTM.TEST.SCHEDULE                             TABLE: IDGS1

COMMAND ===>                                                    SCROLL===> CRSR

OPT  NAME ----- DESCRIPTION ---------------------------------------------------

      IDJOB1     THIS JOB MUST BE RUN BEFORE JOB2

      IDJOB2

      IDJOB3     FISCAL RESULTS ON LAST FRIDAY OF MONTH

  ====== >>>>>>>>>>>>>>>>    NO MORE JOBS IN TABLE     <<<<<<<<<<<<<<<<<<< =====

                                     

                                     

                                     

  

  

  

  

  

  

  

  

  

  

  

  

  

OPTIONS S SEL D DEL I INS O ORDER F FORCE J JCL C COPY P PLN T JOBSTAT 15.37.39

  1. Enter option P for IDJOB3. A window containing FROM DATE and TO DATE fields opens. This window enables you to specify the time period for which the scheduling plan should be displayed.

    Figure 24 Job Scheduling Plan Window

    JOB LIST     LIB: CTM.TEST.SCHEDULE                             TABLE: IDGS1  

    COMMAND ===>                                                    SCROLL===> CRSR

    OPT  NAME -------- DESCRIPTION ------------------------------------------------

         IDJOB1       +---------------------+ FORE JOB JOB2                       

         IDJOB2       |  FROM DATE  020201  |                                     

    P   IDJOB3       |  TO DATE    040301  | FRIDAY OF MONTH                     

    ====== >>>>>     +---------------------+ S IN TABLE     <<<<<<<<<<<<<<<< =====

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

    OPTIONS S SEL D DEL I INS O ORDER F FORCE J JCL C COPY P PLN T JOBSTAT 11.16.50

    The default FROM DATE value is the current working date. The default TO DATE value is one month, or thirty days, following the current working date.

  2. Set the FROM DATE to the first day of the current month. Set the TO DATE to the last day of the current month, and press Enter.

    The Job Scheduling screen is displayed.

    Figure 25 Job Scheduling Screen

    JOB NAME: IDJOB3                 JOB SCHEDULING         DATES : 010201 - 280201

    COMMAND ===>                                                    SCROLL===> CRSR

                                                                                 

       02   2001        MON   TUE   WED   THU   FRI   SAT   SUN                   

                                          01    02    03    04                    

                                                                                 

                                                                                 

                        05    06    07    08    09    10    11                    

                                                                                 

                                                                                 

                        12    13    14    15    16    17    18                    

                                                                                 

                                                                                 

                        19    20    21    22    23    24    25                    

                                                 *                               

                                                                                 

                        26    27    28                                            

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

                                                                                 

    CMDS: NEXT, PREV, END                                                  11.32.19

    The Job Scheduling screen displays a calendar in graphic format. The dates within the specified date range on which the job is to be scheduled are marked with an asterisk.

    Note: If the specified date range spans multiple months, a different calendar panel is displayed for each month, beginning with the first month. You can move between panels by pressing relevant PF keys. PF keys and their associated commands are explained in the following table.

    Table 8 PF Keys and Screen Navigation Commands for
    Job Scheduling Plan Screens

    PF Keys

    Associated Commands

    PF07/PF19

    UP (scroll backward)

    PF08/PF20

    DOWN (scroll forward)

    PF10/PF22

    PREV (where applicable)

    PF11/PF23

    NEXT (where applicable)

    Months in the date range in which the job is not scheduled are not displayed.

    You can also display the Job Scheduling screen from the Job Scheduling Definition screen. To do so, enter PLAN in COMMAND field. This is especially useful for checking your definition of a complex schedule while you are working on it.

  3. Exit the Job Scheduling screen to display the Job List screen.

Parent Topic

Scheduling Definition and Manual Intervention