From the Command field, use the ADD command to add conditions to the IOA Conditions file or resources to the Control-M Resources file.
The format of the command is:
ADD type |
where type is one of the following:
When the ADD command is entered, an appropriate window is opened. The window shown in Figure 84 opens when ADD COND is entered.
Figure 84 IOA Conditions/Resources COND Window
-------------------------- IOA CONDITIONS/RESOURCES ------------------------(4)
COMMAN +---------------------------------------------------------+ L ===> CRSR
PREFIX | PLEASE FILL IN COND NAME, DATE AND PRESS ENTER | 0606 - 0606
OPT TY | | BA DATE
CO | NAME ===> DDMM ===> | 00)
RE | |
RE +---------------------------------------------------------+
RE
RESOURCE TAPEP 01 U 0002 (00091)
RESOURCE CPU1 01 U 0002 (00091)
RESOURCE CPU2 01 U 0003 (00092)
RESOURCE TAPEP 01 R 0002 1 (00093)
COND BR-BRIVPCC-ENDED-OK 0606
COND BR-BRCC0001-ENDED-OK 0606
COND BR-BRCC0002-ENDED-OK 0606
COND BR-BRCC0003-ENDED-OK 0606
COND BR-BRCCIND-ENDED-OK 0606
COND BR-BRUPDT02-ENDED-OK 0606
COND BR-BRREP001-ENDED-OK 0606
COND BR-BRREP002-ENDED-OK 0606
COND GL-GLINP001-ENDED-OK 0606
COND EBD-APPL-STARTED 0606
COND CICS-PROD-IS-UP STAT
OPTIONS: D DELETE C CHANGE ? WHY COMMANDS: ADD 14.07.08
Fill in the window fields as described in Table 106 according to the specified ADD command:
Table 106 IOA Conditions/Resources ADD Command Formats
Format |
Description |
---|---|
ADD COND |
Enter the name of the prerequisite condition. The current working date is displayed as the default date. This date can be modified. |
ADD LCOND |
Same as ADD COND, but for use only when the length of the condition name is from 21 through 39 characters. |
ADD RESOURCE or ADD RES |
Enter the name of the Quantitative resource and the quantity to be added. |
ADD CONTROL or ADD CON |
Enter the name of the Control resource and the control type |
Note: If a Control resource is manually added with a type of E (Exclusive), no jobs in WAIT SCHEDULE status that require this resource are submitted. If a Control resource is manually added with a type of S (Shared), no jobs in WAIT SCHEDULE status that require exclusive access to this resource are submitted. |
After filling in the window, press Enter to add the condition or resource.
To close the window without adding the condition or resource, press the RESET key (PF04/PF16).