Example for SCHEDULE RBC ACTIVE

Rule-based calendar A schedules jobs to run on the 5th of each month. Job B should be scheduled according to the criteria of Rule-based calendar A; however, it should only run until January 15, 2010.

In the SMART Table definition:

SCHEDULE RBC A

DAYS    05         

In job definition B:

SCHEDULE RBC   A                  

RELATIONSHIP (AND/OR)  A              

DAYS ALL

DEFINITION ACTIVE FROM          UNTIL 100115