MAXRERUN Example 1
A tape I/O error occurred. Try two more times. If there are two more failures, terminate:
MAXRERUN 2 RERUNMEM INTERVAL 0015 M FROM END
ON PGMST STEP01 PROCST CODES S613
DO RERUN
MAXRERUN Example 2
When a job abends for any reason, try to restart it two more times (at the abended step).
Figure 242 MAXRERUN Parameter Example 2
JOB: PRDKPL01 LIB CTM.PROD.SCHEDULE TABLE: PRODKPL
COMMAND ===> SCROLL===> CRSR
+---------------------------------------------------------------------------+
===========================================================================
OUT PRDKPL01-ENDED-OK ODAT +
AUTO-ARCHIVE Y SYSDB Y MAXDAYS MAXRUNS
RETENTION: # OF DAYS TO KEEP 030 # OF GENERATIONS TO KEEP
SYSOUT OP (C,D,F,N,R) FROM
MAXRERUN 2 RERUNMEM INTERVAL 0015 M FROM END
STEP RANGE FR (PGM.PROC) . TO .
ON PGMST ANYSTEP PROCST CODES S*** U**** C2000 A/O
DO IFRERUN FROM $ABEND . TO . CONFIRM N
DO RERUN
DO
ON PGMST PROCST CODES A/O
DO
ON SYSOUT FROM 001 TO 132 A/O
DO
ON VAR
DO
SHOUT WHEN TIME + DAYS TO URGN
MS
======= >>>>>>>>>>>>>>>>> END OF SCHEDULING PARAMETERS <<<<<<<<<<<<<<<< ======
COMMANDS: EDIT, DOC, PLAN, JOBSTAT 11.17.00