Adding jobs to be ordered after an event confirmation

This procedure describes how to add jobs to events so that Control-M for SAP can perform the required procedure when the specified event has occurred. The jobs specified should be defined in Control-M before the event takes place.

To add jobs to be ordered after an event confirmation:

  1. From the CCM, right-click the Control-M for SAP component on the host that you want to manage, and select Event Watcher Management.

    The Event Watcher Management dialog box appears.

  2. From the Define Control-M actions to execute after event confirmation area, in the Order Jobs tab, click Add.

    The Add Control-M Job to Order dialog box appears.

  3. In the Job Name field, type the name of the job that you want to add that must begin with a letter and without any blanks or special characters.
  4. In the Folder Name field, type the name of the table that you want to add that must begin with a letter and without any blanks or special characters. In the case of a sub-table, use "/" to separate between table names.
  5. To add specifications that are required to identify the job do the following.
    1. Click Advanced.

      The expanded Add Control-M Job to Order dialog box appears.

    2. In the Scheduling Date area, select one of the following dates:
      • ODAT – Job's order date: Default
      • Any ctmorder date value. Select the required date in the calendar that appears.
    3. In the SMART Folder Parameters area, for each field define the required value as described in SMART Folder Parameters area parameters.
    4. In the Variable area, you can specify new variables to be added to the job.

      Structure: %%<variable name> <variable value>

      For details about variables that are added by default, see Event confirmation default variables.

  6. Click OK.

    The job to be ordered is added to the event.

Parent Topic

Control-M for SAP job ordering