| Option | Description | 
| Calendar Days | Defines the calendar days for scheduling Calendar: The job is scheduled according to the scheduling criteria of the selected Calendar, as described in Calendar management.Exceptions: Schedules or excludes a job on a specific Month Day. Limitations: Limits the scheduling criteria to specific Days of the Week that are selected.Order on Months: Determines the months that can be scheduled for processing.
 | 
| Month Days (Dependent on Calendar) | Defines the days of the Month for scheduling Calendar: The job is scheduled according to the scheduling criteria of the selected Calendar, as described in Calendar management. Intersect with Month Days: The working days in the month are selected when a job should run Exceptions: Schedules or excludes a job on a specific Month Day.Order on Months: Determines the months that can be scheduled for processing.
 | 
| Relative Calendar days from start/end of Month | Defines the relative calendar days from start/end of month for scheduling Calendar: The job is scheduled according to the scheduling criteria of the selected Calendar, as described in Calendar management. Order only on calendar days: Defines the days from beginning of the month or from the end of month (Dn or Ln).Order on Calendar days except: Defines the calendar days from beginning of month or from end of month (-Dn or -Ln).Periods: Enables you to select different periods in a Periodic Calendar, and the calendar days from the beginning or end of each period.Order on Months: Determines the months that can be scheduled for processing.
 | 
| Week Days (Dependent on Calendar) | Defines the days of the week for scheduling Calendar: The job is scheduled according to the scheduling criteria of the selected Calendar, as described in Calendar management. Intersect with Week Days: The working days of the week are selected when the job should run.Exceptions: Schedules or excludes a job on a specific Month Day.Order on Months: Determines the months that can be scheduled for processing.
 | 
| Relative Calendar days from start/end of week | Defines the relative calendar days from start/end of week Calendar: The entity is scheduled according to the scheduling criteria of the selected Calendar, as described in Calendar management.Order only on calendar days: Defines the relative calendar days relative to the start or end of the week.Order on calendar days except: Defines the relative calendar days not included in the scheduling.Week days: Calendar days to order from the beginning of the week.Periods: Enables you to select different periods in a Periodic Calendar, and the calendar days from the beginning or end of each period.Order on Months: Determines the months that can be scheduled for processing.
 |