Status parameters describe information that is collected as the result of a job run, which have the following common characteristics:
status parameters are summarized in the following table:
| Parameter | Description | |
|---|---|---|
| Average Run Time | Average time taken, in minutes, for the job to run. This statistic is compiled from the last successful runs of the job. | |
| Current Status | Indicates the completion status of the job (for example, Ended Not OK). | |
| Deleted | Indicates if the job was deleted. | |
| Due In | Time and day at which the next run of the job should start executing. | |
| + num days | The number of days that the start of job execution is extended after the ODAT. This sub-parameter is relevant only for jobs running under Control‑M for z/OS version 6.2.00 or later. | |
| Due Out | Time and day by which the next run of the job should stop executing. | |
| Format | HHMM, where HH is a 2-digit number from 00 through 24. | |
| + num days | The number of days that the end of job execution is extended after the ODAT. This sub-parameter is relevant only for jobs running under Control‑M for z/OS version 6.2.00 or later. | |
| Elapse | Length of time (in minutes) that the job is expected to run. | |
| End Time | Indicates the time that the last run of the job ended. NOTE: You must use the following format: YYYYMMDDhhmmss | |
| From Proc | For z/OS jobs only with Control-M/Restart: Procedure step from which the job should be rerun. | |
| From Step | For z/OS jobs only with Control-M/Restart: Step from which the job should be rerun. | |
| Hold | Indicates if the job is currently being held. | |
| Job ID | Unique serial number assigned to the job by the Control‑M server. | |
| Next Time | Determines the next time that the job runs for reruns or cyclic jobs that use the Interval option. | |
| NJE | Indicates that the job was sent for execution to a computer that is connected to Control-M through NJE (the node does not have a shared spool with Control-M). | |
| NJE Node | Node ID of the NJE terminal. | |
| Rerun Counter | Indicates how many times the job was run. | |
| Restart | Indicates if the job was restarted. | |
| Search Count | Number of times Control-M has looked for the job. | |
| Standard Deviation | Standard deviation from the average runtime. This statistic is compiled from the last successful runs of the job. | |
| Start Time | Indicates the time that the last run of the job started. NOTE: You must use the following format: YYYYMMDDhhmmss | |
| To Proc | For z/OS jobs only with Control-M/Restart: Procedure step until which the job should be rerun. | |
| To Step | For z/OS jobs only with Control-M/Restart: Step until which the job should be rerun. | |