Connecting the gateway to the new Control-M/Server

This procedure describes how to connect the gateway to the new Control-M/Server. Perform this procedure if Control-M/EM was not migrated at the same time as Control-M/Server, and you want to reuse the Control-M/Server component in the CCM.

To connect the gateway to the new Control-M/Server

  1. Log in to the Control-M/EM client in the new environment and open Control-M Configuration Manager (CCM).
  2. From the CCM, select the Control-M/Server that was migrated, right-click and select Properties.
  3. In the left pane, click Communication.
  4. Update the Host and Control-M/EM Port fields to the location of the new Control-M/Server, and then click OK.
  5. Recycle the gateway.

Parent Topic

Post-Control-M/Server migration procedures